CONSTRUCTION PROJECT UPDATES: 6/23/23

CONSTRUCTION PROJECT UPDATES: 6/23/23

Chestnut Street, Locust Street, & Spruce Street Water Main and Street Improvement Project

This week the contractor completed the remainder of the concrete the sidewalk as well as concrete and asphalt driveway apron restorations.   The landscape restoration also began on the project.  The pavement was removed on all three of the streets.

On Saturday, the contractor is planning to begin installing the aggregate base.  If they do not complete the stone installation on Saturday, they plan to continue Monday.

Mid next week they plan to begin installation of the first layer of asphalt on all three of the streets.