2022 Road Program Update
This past week Geneva Construction was able to finish the few asphalt apron restorations that remained. Unfortunately, no work had occurred with paving the streets due to the ongoing labor dispute at the local aggregate production facilities. Until the labor dispute is resolved, the placement of the surface layer of asphalt is going to continue to be delayed.
The Village is actively working with Geneva Construction to get their landscape subcontractor back out to the project to complete the brick paver driveway restorations.