Skip to content

An Attentive Municipal Organization that Connects with Community, Commerce, and Nature.

Construction Project Updates


Construction Project Updates September 4, 2020

2020 Street Improvements
The contractor is working on scheduling pavement striping and the restoration of disturbed areas on Maple, Elm, and Locust, and at locations where sidewalk was removed and replaced. It is anticipated these activities will start in the coming weeks.

Silo
This week the tree removal has been completed. Currently the general contractor is coordinating the lift rental to coincide with the delivery of the steel.  It is anticipated this will occur within the next two weeks.  Staff is also coordinating a response to a request for information from the electrical contractor.

Village of North Aurora

Install Village of North Aurora

Install this application on your home screen for quick and easy access when you’re on the go.

Just tap then “Add to Home Screen”