Construction Project Updates July 2


 

Construction Project Updates July 2, 2020

Well Number 8 & 9
This week Village Staff continued collecting and preparing information for the IEPA to issue an operating permit.  Wednesday the IEPA issued verbal approval for both wells.  

Maple and Elm Water Main
Both streets have passed their chlorination testing.  This week the contractor was delayed by the weekend rain and the short week for the holiday. Water services installation will begin on Elm Street next week.   

2020 Street Improvements
This week Geneva Construction completed paving and restoration on April, Arrowhead, Briar, Dee, and Laurel.  A list of punch list items are being compiled for the contractor.

Maple and Elm will occur after the water main replacement project is complete.

Silo
The demolition contractor completed the removal of items from the interior of the silo and the removal of the Christmas tree from the top.  Tree trimming of trees in the area is scheduled for Monday.   The concrete restoration is also scheduled to start Monday.  

Village of North Aurora

Install Village of North Aurora

Install this application on your home screen for quick and easy access when you’re on the go.

Just tap then “Add to Home Screen”

Accessibility Toolbar