Skip to content

An Attentive Municipal Organization that Connects with Community, Commerce, and Nature.

Construction Project Updates: June 9, 2023

Construction Project Updates: June 9, 2023

Chestnut Street, Locust Street, & Spruce Street Water Main and Street Improvement Project

 

This week the contractor completed the concrete sidewalk curb removal on the opposite side of the street that had concrete restoration completed.

 

On Monday, the contractor is planning to place stone, frame, and prepare the concrete curb and sidewalk.  Tuesday, they plan to pour the concrete curb on all three streets.  Wednesday, they plan to pour the concrete sidewalk on all three streets.   The remainder of the week they plan to begin the grass restoration on the side of the streets that had been previously completed with concrete restoration.

 

2023 Road Program

This week the contractor completed the remainder of the asphalt surface paving and the asphalt apron restorations.

 

Next week, the contractor will be continuing the grass restoration and general project area clean up.

Village of North Aurora

Install Village of North Aurora

Install this application on your home screen for quick and easy access when you’re on the go.

Just tap then “Add to Home Screen”

Accessibility Toolbar