2022 Road Program Update This week, Geneva Construction placed the last of the binder course on Pinecreek Drive. Additionally, the surface course was poured on Matthias Court, Slaker Court, and Dewig Court. A prime coat was put on Spyglass Court, Augusta Drive, Meadow Lane, Winterberry Court, Aster Court, Greenbriar Court, and some of… Read More
2022 ROAD PROGRAM UPDATES
This week Geneva Construction completed the remaining asphalt roadway pavement removal on Pinecreek. They completed the first layer of asphalt on Doral, Dewig, Slaker, Hammer, Matthias and the majority of Pinecreek. They also completed the surface layer (final layer) of asphalt on Turnberry, Coghill, Clark, Cantigny, and Oak Crest. Landscape restoration was substantially completed throughout… Read More
Attention: Warning About Red-Wing Blackbirds at North Aurora Riverfront Park
ATTENTION For any visitors to North Aurora Riverfront Park specifically by the lower end of Water Wonders (see below photo), there is a red-winged blackbird nest in the area. Red-wing blackbirds are highly protective of their nests and will swoop down in an effort to protect it. Please use caution if you are in the… Read More
2022 Road Program Updates
Geneva Construction completed the asphalt roadway pavement removal on Woodlawn, Columbia, Wingfoot, Doral, Spyglass, Dewig, Slaker, Hart, Matthias, and Hammer. They completed partial removal on Pinecreek. They completed the first layer of asphalt on Fairfield, Hartfield, Aster, Meadow, Winterberry, Woodlawn, Columbia, Wingfoot, Hart, Spyglass, part of Doral, and part of Pinecreek . Landscape restoration… Read More
Village of North Aurora July 3rd Celebration Information!
Village of North Aurora July 3rd Celebration Information! The Village of North Aurora will be holding our Independence Day celebration and fireworks show on Sunday, July 3 at Riverfront Park (25 East State Street), which is right next to Village Hall. The event starts at 5pm and goes until the end of the fireworks show,… Read More
2022 Road Program Updates
Geneva Construction completed almost all of asphalt driveway restorations on the project. There are a few remaining that they plan to complete next week. They completed the asphalt roadway pavement removal on Augusta, Hartfield, Fairfield, Greenbrier, Aster, Meadow, and Winterbury. They completed partial removal on Woodlawn, Columbia, Wingfoot, and the north section of Doral. They… Read More
Proclamation Issued in Support of National Safe Boating Week
At last week's Village Board meeting, Mayor Gaffino issued a proclamation in support of National Safe Boating Week, which runs from May 21 - May 27, 2022. National Safe Boating Week brings attention to the life saving measures of wearing life jackets, boat safety checks, and other safety procedures. As the Village of North Aurora… Read More
2022 ROAD PROGRAM UPDATE
2022 Road Program This week D’Land completed almost all of the remaining concrete work on the project, which included pouring concrete on Wingfoot, Columbia, Doral, Slaker, Matthias, Dewig, and Pinecreek. Any remaining concrete is anticipated to be completed on Monday. Geneva Construction completed asphalt driveway restoration on Columbia, Wingfoot, Fairfield, Hartfield, Greenbrier, Aster, Winterberry, and… Read More
Mayor Gaffino Attends Women's Council of Realtors of the Fox Valley Mayor's Panel
Mayor Gaffino recently participated in the Women's Council of Realtors Fox Valley Mayor's Panel. Mayor Gaffino was able to speak to attendees about upcoming Village events, new commercial and residential developments, and what makes North Aurora a great community to live in! … Read More
2022 Road Program Update
2022 Road Program Geneva Construction had a change in their schedule and is now planning to begin with the asphalt pavement removal tomorrow, May 19th. They will be beginning on Oak Crest, Turnberry, Clark, Coghill, and Cantigny. On Friday, they will continue with pavement removal on Augusta, Fairfield, Derby, Greenbrier, and northwest portion of Hartfield,… Read More