2022 Road Program

Geneva Construction  had a change in their schedule and is now planning to begin with the asphalt pavement removal tomorrow, May 19th.  They will be beginning on Oak Crest, Turnberry, Clark, Coghill, and Cantigny.  On Friday, they will continue with pavement removal on Augusta, Fairfield, Derby, Greenbrier, and northwest portion of Hartfield, pending the landscaper has completed topsoil placement on those streets.

 

During the pavement removal process and while they contractor is working on aggregate base repairs and paving the streets, please park your vehicles in your driveway or garage during construction hours.  Typically from 7 AM to 4 PM on weekdays.

 

Streets and driveways will remain accessible throughout the duration of the pavement removal, base repairs, and paving of the streets.  There may be minor delays accessing driveways when the removal or paving is happening directly in front of your driveway.

 

After the pavement removal, the streets will be gravel until the contractor places the first layer of asphalt.  The contractor will be placing stone ramps at the end of each driveway to maintain access.

Additional work may take place on other streets not listed above at the contractors’ discretion.

Village of North Aurora

Install Village of North Aurora

Install this application on your home screen for quick and easy access when you’re on the go.

Just tap then “Add to Home Screen”

Accessibility Toolbar