2022 Road Program

This week Geneva Construction’s concrete subcontractor, D’Land Construction, continued saw cutting curb and sidewalk in preparation for removals completing saw cutting on Augusta, Oak Crest and part of Doral.    On Friday they will be continuing to cut on Fairfield and then next week continuing on Greenbrier, Fairfield, Aster, Winterberry, and Meadow.

 

This week the Contractor removed curb and sidewalk on Turnberry, Coghill, Clark, Oak Crest, and Augusta.  They are planning to remove the curb and sidewalk on Greenbrier, Fairfield, Aster, Winterberry, and Meadow over the next week.

 

The contractor began framing the curb and sidewalk on Thursday starting at Turnberry and Coghill and will be continuing to frame following the path of the removal.

 

The first concrete pour is scheduled for Monday beginning on Turnberry and Coghill.  With pouring more curb and sidewalk each subsequent day in the order of the framing installation.