Construction Project Updates September 16


Construction Project Updates September 16, 2019

Well Number 8  & 9 Transmission Mains
Patnick Construction has completed the Well 9 Transmission mains.  The Well #8 transmission main installation project has begun with the surveyors completing the construction layout. We are awaiting the constructor’s schedule.

Well Number 8 & 9 Pumps and Motors
The Village received bids for the pump and motor contract. This contract was awarded to Layne Christensen at the August 19, 2019 Village Board meeting. Contracts have been signed and the next step will be to approve shop drawings.

Well Number 8 & 9 Well Building and Electrical
The Village received bids for this project on September 6, 2019.  The Village Board will be considering staff recommendations and taking action at the September 16, 2019.

2019 Street Improvements

  1. Summerwind: East Victoria Circle and Hidden Creek Avenue.

Pavement striping and punch list compilation is starting soon.

  1. Orchard Crossings: Westbury Circle, Forest Ridge Drive, Alexandra Court, Oakland Circle, Waterford Road, Fechner Circle, Messenger Circle, Hartsburg Lane, Hawksley Lane, Whalen Court, and Ritter Street

Corrective work needs to be performed on Messenger Circle.  Milling of the problem was completed this week. Paving of the milled area and punch list compilation and pavement striping will follow.

  1. Waterford Townhomes: Waterford Road, Kathryn Lane, and Arbington Lane.

Pavement striping and punch list compilation is starting soon.

  1. Patching: Arrowhead, April, Dee,  and Laurel 
    Pavement Patching has been marked out in white paint, this operation is expected to resume in September.

 

  1. Deerpath and Orchard Gateway: Intersection Repair (North Leg)
    Pavement striping and punch list compilation is starting soon.

 

If you need additional information regarding the Road Project please contact our construction inspectors. Rick Pace at 630.310.7574 or Eric Johnson 630.846.0830.

Silo
Bids were rejected at the August 5, 2019 Village Board meeting. Staff has met with a general contractor and is exploring a path forward for the rehabilitation and illumination of the silo.

LED’s
A preconstruction meeting was held with the contractor Utility Dynamics.  The contractor has indicated that work will begin in mid-October and completed by December 1, 2019.  The starting location will be determined before installation begins.

Tree Planting Program
Staff will be visited the nursery on September 4, 2019 and selected the 100 trees schedule to be planted by November 1, 2019.  

Route 25 Paving Project (Lincoln Valley)
The final course of asphalt was placed on Route 25 at the entrance of Lincoln Valley.  Pavement striping will be placed on Saturday September 14, 2019.

 