Skip to content

An Attentive Municipal Organization that Connects with Community, Commerce, and Nature.

2022 Road Program Update

2022 Road Program Update

This week D’Land continued with pouring concrete on Turnberry, Clark, Oak Crest, Augusta, Hartfield (Augusta to Greenbrier), and Fairfield. They also removed curb and sidewalk on Aster, Meadow, and Winterberry in preparation for next week.

 

Next week D’land plans on continuing to pour concrete on all the streets that have recently had the concrete removed. Removals will continue on Hartfield, Doral (North of Wingfoot, one side at a time), Columbia, Woodlawn, and then Doral (south of Wingfoot) if time allows. Saw Cuts will continue ahead of removals for the entire project.

 

Geneva Construction plans to begin asphalt driveway patches early-mid next week.

Village of North Aurora

Install Village of North Aurora

Install this application on your home screen for quick and easy access when you’re on the go.

Just tap then “Add to Home Screen”