Construction Project Updates August 28, 2020 2020 Street Improvements The contractor is working on scheduling pavement striping and the restoration of disturbed areas on Maple, Elm, and at locations where sidewalk was removed and replaced. It is anticipated these activities will start in the coming weeks. Silo This week Public Works staff researched camera… Read More
Community Garage Sale
While North Aurora Days 2020 may have been cancelled, we’re happy to announce that the Community Garage Sale is still on! This yearly event is one we feel residents can safely participate in while adhering to social distancing measures and we hope everyone has a fun, safe time. All North Aurora residents are invited to… Read More
Candidate Packets Available
Notice is hereby given that North Aurora Village Hall will have candidate packets available weekdays from 8:00 a.m. to 4:30 p.m. beginning August 24, 2020. Petitions may not be circulated prior to August 25, 2020.… Read More
Construction Project Updates August 21, 2020
Construction Project Updates August 21, 2020 2020 Street Improvements Friday August 21, the contractor is scheduled to complete the paving on Maple & Elm. Next week any remaining restoration and punch list items will be addressed. Silo This week Public Works installed a conduit around the perimeter of the silo that will house the… Read More
Village Board Meeting Zoom Information
The Services Committee meeting and the Village Board meeting on July 20, 2020 at 6:00 p.m. and 7:00 p.m respectively will be held electronically using the Zoom conference platform. If you wish to speak during the audience comment portion, please use the "Raise your Hand" feature of the Zoom meeting or message the meeting host… Read More
Construction Project Updates August 14
Construction Project Updates August 14, 2020 2020 Street Improvements This week the contractor finished all village wide hot-mix asphalt driveway patches, finished all curb and gutter on Maple & Elm, and restored access where possible to all residents on Maple & Elm. Next week Geneva Construction plans on finishing all hot-mix asphalt driveway patches… Read More
Update: North Aurora Village Hall Closed Until Monday, August 17
Update: North Aurora Village Hall will remain closed through the rest of this week and will tentatively reopen on Monday, August 17. All employees will be working remotely and the public is welcome to call Village Hall at 630-897-8228 and conduct business via phone and / or email. Original post: Due to a precaution, North Aurora… Read More
Construction Project Updates August 7, 2020
Construction Project Updates August 7, 2020 2020 Street Improvements This week the contractor completed the replacement of the all of the miscellaneous concrete sidewalk replacement and the spot repairs on the 400 block of Locust. They have also removed and replaced half of the curb and gutter on Maple and Elm to provide adequate… Read More
Village Board Meeting Zoom Information
Village Board Meeting Zoom Information The Village Board meeting on August 3, 2020 at 7:00 p.m. will be held electronically using the Zoom conference platform. If you wish to speak during the audience comment portion, please use the "Raise your Hand" feature of the Zoom meeting or message the meeting host using the chat feature.Below… Read More
Construction Project Updates July 31, 2020
Construction Project Updates July 31, 2020 Well Number 8 & 9 Wells number 8 & 9 are being integrated into the computer system. The performance and production of both wells will be monitored over time. No further updates on this project will be included in future construction project updates. 2020 Street Improvements This week… Read More