Skip to content

An Attentive Municipal Organization that Connects with Community, Commerce, and Nature.

Construction Update: June 28

Construction Update: June 28

June 28

2024 Road Program

This week the contractor removed additional concrete curb and sidewalk on Silver Trail, Harmony, and Hickory as well as framing and preparing for the concrete placement.  They poured concrete curb and sidewalk on part Harmony, Anna, Flagstone, Hickory, and Ridge.  Unfortunately, due to the rain this week less than originally planned was accomplished.  For pouring new concrete it cannot be raining and the hole where the concrete is being placed needs to not have standing water.  When they are unable to place new concrete, it may also stop the progress of their removal operations to avoid getting too far ahead of the crew placing the concrete.

On Saturday, the contractor plans to work continuing to frame and prepare for concrete placement on Silver Trail.

On Monday, the contractor plans to place concrete on Silver Trail.  Tuesday placing concrete on Hickory.  The first half of the week they would be removing the portions of Ridge, Harmony, and Silver Trail that still need concrete to be removed.  They also will be continuing to follow behind the removals with framing and prepping, followed by pouring the concrete in those areas.   Mid to late next week they project starting removals in the Oak Hill subdivision.

June 21

2024 Road Program

The contractor had continued to saw cut the concrete items for removal on the western portion of the project, they plan to continue saw cutting next week and planning on finishing the saw cutting.

 

The contractor began removing concrete curb and sidewalk on Ridge, Sharon, Flagstone, April, Hickory, Harmony and Silver Trail this week.  They have followed behind the removals with framing and preparing for the concrete placement.  On Thursday, they poured concrete curb and sidewalk on part of Ridge, Sharon and Flagstone.  The contractor also began curbline drainage structure repairs on Ridge.

 

On Saturday, the contractor plans to work continuing to frame and prepare for concrete placement.

 

Next week the contractor will continue with concrete removals on Harmony and Silver Trail, then heading to the Oak Hill subdivision and then possibly later in the week, removing the portions of Ridge and Hickory that still need to be removed.  They also will be continuing to follow behind the removals with framing and prepping, followed by pouring the concrete.  On Tuesday, they are planning their next concrete pour on Hickory, Flagstone, and April.

 

For concrete replacements done through driveways, the contractor will remove the barricades once the concrete has cured enough to allow for vehicle traffic.

June 14

2024 Road Program

This week the contractor began saw cutting the concrete curb in the project area east of the Fox River.  They plan to continue saw cutting on Saturday.

Next week the contractor will continue saw cutting.  After completing the saw cutting east of the river, they will saw cut on Harmony and Silver Trail then moving to the Oak Hill subdivision and Windstone subdivision.

On Monday, the Contractor also plans to begin the concrete removals on Ridge Rd.  When they finish removals on Ridge, they will continue to complete removals on the other streets on the east side of the river.  The Contractor will post notices adjacent to driveways that will have their access removed at least 24 hours in advance of the removals.

 

June 10

2024 Road Program

This week the contractor plans to start saw cutting the concrete curb and sidewalk that is planned to be removed as a part of the project.  They anticipate starting as early as Wednesday, beginning on the area of the project that is east of the Fox River (Hickory, Flagstone, Sharon, Ridge, Anna).  Once they complete this area they will be working their way west.

Saw cutting will not affect driveway access, but please be aware that there is a slurry created from the cutting that can be tracked until it dries.

Village of North Aurora

Install Village of North Aurora

Install this application on your home screen for quick and easy access when you’re on the go.

Just tap then “Add to Home Screen”

Accessibility Toolbar