CONSTRUCTION PROJECT UPDATES FOR JUNE 18, 2021

CONSTRUCTION PROJECT UPDATES FOR JUNE 18, 2021

2021 Street Improvement

This week Geneva Construction continued with concrete removals completing Bede, Carrie Court and Lloyd Lane, with partial removal of Lindsay Circle and Terry Lane.

 

The concrete crew continues to follow the path of the removal crew. This week they poured all curb & gutter on Hickory Street, Hickory Court, Andrew Lane, Andrew Court, Sharon Lane, Sharon Court, Bede Circle, Bede Court,  Lloyd Lane, and after today a large amount of Lindsay Circle.

 

Following closely behind the concrete crew is the asphalt patch crew, completing driveways and giving access back to residents. After today, patches will be complete on Andrew Lane, Andrew Court, Hickory Street, Hickory Court, Sharon Lane, and Sharon Court.

 

Next week Geneva Construction’s removal crew plans on completing the concrete removal on Lindsay Circle, Terry Lane, and Holly Court on Monday & Tuesday. Concrete pouring continuing to follow the removal crew, with hopes of completing all concrete by end of the week. Landscapers are scheduled to start on Monday at the north end of the project. Pavement milling is tentatively scheduled to begin mid to late next week at the northern end of the project.

 

Village of North Aurora

Install Village of North Aurora

Install this application on your home screen for quick and easy access when you’re on the go.

Just tap then “Add to Home Screen”

Accessibility Toolbar