🚧 Construction Project Updates
Chestnut Street, Locust Street, & Spruce Street Water Main and Street Improvement Project
The contractor completed concrete punch list items prior to placing the final asphalt surface on the street.
The contractor is planning to pave the final layer of asphalt pavement on all three streets this Friday, July 28th, weather pending.