Skip to content

An Attentive Municipal Organization that Connects with Community, Commerce, and Nature.

2022 Road Program Update

2022 Road Program Update

🚧 2022 Road Program Update
This week D’Land poured concrete on Wingfoot, Columbia, Doral, Dewig, and Pinecreek. They also removed curb and sidewalk on Pinecreek, Dewig, Doral, Columbia, and Wingfoot.
Next week D’land plans on completing all of the remaining concrete removals on Doral, Slaker, and Hammer on Monday. They also plan to complete pouring all of the remaining concrete on the project next week. This work is primarily on Wingfoot, Doral, Slaker, Hammer, and Pinecreek.
Geneva Construction plans to continue with asphalt driveway restoration next week beginning on Fairfield, Hartfield, Greenbrier, Aster, Winterberry, and Meadow. They will continue on to other streets if time allows. Landscape restoration is anticipated to begin next week, starting on Turnberry, Clark, and Oak Crest.
Additional work may take place on other streets not listed above at the contractors’ discretion.
Village of North Aurora

Install Village of North Aurora

Install this application on your home screen for quick and easy access when you’re on the go.

Just tap then “Add to Home Screen”

Accessibility Toolbar